Current through Register 1538, January 3, 2025
Section 2.07 - Notice to Proceed(1)Issuance of Notice to Proceed. The Inspector General shall issue a Notice to Proceed to use construction management at risk services to an awarding authority once the awarding authority has met the requirements as prescribed by the Inspector General. At a minimum, the awarding authority will be required to demonstrate that it has the authority and capacity to proceed; that it has a plan and procedures to effectively procure and manage the project; that it has retained a qualified owner's project manager; that it has retained a qualified designer; and, that it has procedures to ensure fairness in competition, evaluation, selection, and reporting.(2) After receiving a notice to proceed, an awarding authority may use the construction management at risk delivery method. The awarding authority shall procure a construction management at risk firm in a manner consistent with M.G.L. c. 149A, § 5 through 11 and 945 CMR 2.00.