810 CMR, § 9.02

Current through Register 1536, December 6, 2024
Section 9.02 - Mandatory Prequalification of General Contractors

For all contracts subject to M.G.L. c. 149, § 44A where the estimated construction cost for a Building Project is not less than $10,000,000, all Awarding Authorities, other than the Exempt Agencies, shall prequalify all General Contractors to submit general bids. The provisions of 810 CMR 9.00 do not apply to prequalification of General Contractors in the context of a Building Project being undertaken using a Construction Manager at Risk delivery method under M.G.L. c. 149A.

810 CMR, § 9.02

Amended by Mass Register Issue 1428, eff. 10/16/2020.