Current through Register 1533, October 25, 2024
Section 4.07 - Rating of Project Performance(1)Standard Contractor Evaluation Form. The Standard Contractor Evaluation Form shall be used to rate the Contractor on a single Building Project according to criteria established by the Commissioner for assessing the performance of the Contractor on the project.(2)Project Rating. The representative of the Awarding Authority or private Building Project owner evaluating the Contractor's performance on the project shall score the contractor on each performance criterion. The Contractor's Project Rating for the project shall be the total of the scores given for each criterion.(3)Average Project Rating. DCAM shall assign each Contractor an Average Project Rating which shall be the average of Project Ratings given to the Contractor for all of the evaluated Building Projects completed within the time frame established by M.G.L. c. 149. The Contractor's performance on projects shall be considered satisfactory only if the Average Project Rating meets or exceeds the minimum rating outlined in the Guidelines.