780 CMR, ch. 13

Current through Register 1538, January 3, 2025
Chapter CHAPTER 1 [CE] - SCOPE AND ADMINISTRATION

SECTION C103 CONSTRUCTION DOCUMENTS

Add the following to Section C103.2: C103.2 Information on construction documents

14. Solar Ready roof zone in accordance with Appendix CB.
15. EV Ready Spaces locations in accordance with C405.13

Add the following Section C103.2.2:

C103.2.2COMcheck submittal. The construction documents submitted with the application for permit shall be accompanied by completed COMcheck Envelope, Lighting and Mechanical Compliance Certificates, and a Plan Review Inspection Checklist for the purposes of demonstrating compliance with the energy provisions of 780 CMR 13.00: Energy Efficiency.

780 CMR, ch. 13

Amended by Mass Register Issue 1532, eff. 10/11/2024.