Subsection 110.6 - Approval Required

Work shall not continue beyond the point indicated in each successive inspection without first obtaining the approval of the building official. Upon notification, the building official, shall make the requested inspections and shall either indicate the portion of the construction that is satisfactory as completed, or notify the permit holder or his or her agent wherein the same fails to comply with 780 CMR. Any portions that do not comply shall be corrected and such portion shall not be covered or concealed until authorized by the building official.

780 CMR, ch. 1, pt. 2, 110, 110.6

Amended by Mass Register Issue 1532, eff. 10/11/2024.