780 CMR, ch. 1, pt. 2, 109, 109.3

Current through Register 1538, January 3, 2025
Subsection 109.3 - Building Permit Valuations

The applicant for a permit shall provide an estimated value of project cost at time of application. If, in the opinion of the building official, the valuation is underestimated on the application, the permit shall be denied, unless the applicant can show detailed estimates to meet the approval of the building official. Final building permit valuation shall be set by the building official.

780 CMR, ch. 1, pt. 2, 109, 109.3

Amended by Mass Register Issue 1532, eff. 10/11/2024.