780 CMR, ch. 1, pt. 2, 107, 107.4

Current through Register 1538, January 3, 2025
Subsection 107.4 - Amended Construction Documents

Work shall be installed in accordance with the approved construction documents. Any changes made during construction that are not in compliance with the approved construction documents shall be resubmitted for approval as an amended set of construction documents prior to the commencement of the proposed work.

780 CMR, ch. 1, pt. 2, 107, 107.4

Amended by Mass Register Issue 1532, eff. 10/11/2024.