In accordance with the provisions of M.G.L. c. 146, § 2, the Board adopts 2019 NBIC Part 2.
The First Inspection for the installation of a Hot Water - Low Pressure/Heating Boiler or heat storage source covered by 522 CMR 4.05 may be made by either a District Engineering Inspector or by an Authorized Inspector. The first part of the inspection on steel field-erected Boilers shall be completed before the system is filled with the fluid to be heated.
The First Inspection for the installation of a steam Boiler covered by 522 CMR 4.05 shall be made by a District Engineering Inspector.
If a Boiler has not been properly cooled or otherwise prepared for inspection, the District Engineering Inspector or Authorized Inspector shall decline to inspect the Boiler until the Boiler has been properly prepared.
The Authorized Inspector shall notify the Chief or his or her designee immediately in writing if the Authorized Inspector finds that an unsafe and dangerous condition exists resulting in the removal of the Certificate.
If upon review of this information, the Board finds that the Boiler is in compliance with the Massachusetts requirements with regard to material, construction, and workmanship, and further finds that the Boiler is in safe working condition and equipped with all necessary appendages, the Board shall issue a Certificate establishing the safe working pressure.
522 CMR, § 4.05