Section 45.09 - Project Evaluation Report
(1) Unless otherwise determined by the Department, the planning information required for projects receiving financial assistance pursuant to 310 CMR 45.00 shall be contained in a Project Evaluation Report.
(2) The Department will determine the required scope of a Project Evaluation Report based on the nature and duration of the proposed project. Unless otherwise determined by the Department, a complete Project Evaluation Report generally must include:
(a) A description of the proposed project;
(b) An analysis of the cost-effectiveness of the project and the alternatives considered;
(c) For the selected alternative, a concise description which addresses, at a minimum, the following areas:
1. the relevant design parameters for the project;
2. the estimated capital construction and operation and maintenance costs of the project (identifying possible federal, state, local, and other shares), and a description of the manner in which costs will be financed;
3. the cost impacts on users of the system; and
4. the institutional, financial, legal and management arrangements necessary for successful implementation of the project.
(d) A public participation program that includes, at a minimum:
1. a public informational meeting to discuss the project alternatives and their environmental impact; and
2. a subsequent public hearing on the selected proposed project, including its environmental impact.