Section 40.0879 - Phase IV Completion Statement
(1) A Phase IV Completion Statement form, established by the Department for such purposes, shall be appended to and submitted with the Final Inspection Report to the Department.
(2) A Completion Statement form submitted with a Final Inspection Report shall include the following:
(a) an Opinion from a Licensed Site Professional as to whether the construction and implementation of the selected Comprehensive Remedial Alternative has been completed in accordance with applicable requirements of 310 CMR 40.0870, and the Phase IV performance standards as described in 310 CMR 40.0872 have been met;
(b) a certification of the submittal required by 310 CMR 40.0009; and
(c) an indication as to whether any activities under Phase V will be conducted as part of the implementation of the selected Comprehensive Remedial Alternative.
(3) Upon receipt of a Phase IV Completion Statement in accordance with 310 CMR 40.0879 which indicates that any Phase V activities pursuant to 310 CMR 40.0890 are required at a disposal site, the Department shall suspend the further assessment of Tier I or Tier II Annual Compliance Assurance Fees, whichever are applicable, and shall assess a Phase V - Operation Maintenance and/or Monitoring Compliance Assurance Fee pursuant to 310 CMR 4.00: Timely Action Schedule and Fee Provisions.