310 Mass. Reg. 40.0875

Current through Register 1523, June 7, 2024
Section 40.0875 - As-built Construction Report
(1) As-built Construction plans shall be prepared and submitted to the Department in an As-built Construction Report for:
(a) any disposal site where an Engineered Barrier, cap or other on-site system for the containment and/or physical immobilization of oil and/or hazardous material is constructed as part of the Remedial Action Alternative; or
(b) any disposal site where the Comprehensive Remedial Alternative as actually constructed varies significantly from the description of the alternative provided in the RIP under 310 CMR 40.0874.
(2) The As-built Construction Report shall include, without limitation, the following information:
(a) construction activities conducted, and techniques and materials used;
(b) tests and measurements performed;
(c) any significant modifications of the design or construction of the selected Comprehensive Remedial Alternative as described under 310 CMR 40.0874(3)(c) of the RIP; and
(d) as built drawings.
(3) As-built plans for the Comprehensive Remedial Action shall be prepared in conformance with appropriate engineering and construction standards and practices, and regulations applicable to construction plans and activities.

310 CMR 40.0875

Amended by Mass Register Issue 1503, eff. 3/1/2024.
Amended by Mass Register Issue S1516, eff. 3/1/2024.