Current through Register 1536, December 6, 2024
Section 19.011 - Signatories, Certification and Engineer's Supervision(1)Signatories and General Certification. Any application for a permit, authorization to construct, authorization to operate, permit modification, and any determination, certification, report and any other document submitted to the Department pursuant to 310 CMR 19.000, shall be signed by the appropriate responsible official. Any person required by 310 CMR 19.000 or any order or other enforcement document issued by the Department, to submit any document to the Department shall identify himself or herself by name, profession, and relationship to the applicant and legal interest in the facility, and make the following statements: I, [name of responsible official], attest under the pains and penalties of perjury that:
(a) I have personally examined and am familiar with the information contained in this submittal, including any and all documents accompanying this certification statement;(b) based on my inquiry of those persons responsible for obtaining the information, the information contained in this submittal is, to the best of my knowledge, true, accurate, and complete;(c) I am fully authorized to bind the entity required to submit these documents and to make this attestation on behalf of such entity; and(d) I am aware that there are significant penalties, including, but not limited to, possible administrative and civil penalties for submitting false, inaccurate, or incomplete information and possible fines and imprisonment for knowingly submitting false, inaccurate, or incomplete information; and(e) (for a responsible official submitting a third-party inspection report pursuant to 310 CMR 19.018(8)(b)1.) The facility [name of facility] provided any information required by 310 CMR 19.018 and requested by the third-party inspector in a timely fashion and any employee or contractor of [name of facility] did not unduly influence the third-party inspector; and(f) (for a responsible official submitting a transfer station certification pursuant to 19.035(4)): 1. I have accurately stated whether the transfer station is in compliance with its permit and all other applicable requirements in 310 CMR 16.00: Site Assignment Regulations for Solid Waste Facilities and 19.000 including, but not limited to, 310 CMR 19.043;2. I have accurately identified any and all violations of 310 CMR 16.00: Site Assignment Regulations for Solid Waste Facilities or 19.000 or the terms and conditions of any permits or other approvals issued thereunder by the Department;3. If the transfer station is not in compliance, I have stated what the owner and operator will do to return the transfer station to compliance and the date by which compliance will be achieved; and,4. Plans and procedures to maintain compliance are in place at the transfer station and will be maintained even if processes or operating procedures are changed.(2)Engineering Supervision. 310 CMR 19.011(2) does not apply to any documents submitted to the Department pursuant to 310 CMR 19.018. All papers pertaining to design, construction, operation, maintenance, or engineering of a site or a facility shall be completed under the supervision of a Massachusetts registered professional engineer knowledgeable in solid waste facility design, construction and operation and shall bear the seal, signature and discipline of said engineer. The soils, geology, air modeling, air monitoring and groundwater sections of an application or monitoring report shall be completed by competent professionals experienced in the fields of soil science and soil engineering, geology, air modeling, air monitoring and groundwater, respectively, under the supervision of a Massachusetts registered professional engineer. All mapping and surveying shall be completed by a registered surveyor.