Where M.G.L. c. 131, § 40 states that an order or notification shall be signed by a majority of the conservation commission, that action is to be taken by a majority of the members then in office, who need not convene as a body in order to sign, provided they met pursuant to the open meeting law, M.G.L. c. 39, §§ 23A through 23C, when voting on the matter.
Where M.G.L. c. 131, § 40 states that the conservation commission is to receive a request or notice, conservation commission means a member of the conservation commission or an individual designated by the conservation commission to receive such request or notice.
Any person who proposes to apply herbicides in the Buffer Zone pursuant to the presumption of 310 CMR 10.03(6)(b) shall be required only to submit a request for determination of the boundaries of the Buffer Zone and the Areas Subject to Protection under M.G.L. c. 131, § 40. Such Request for Determination shall be submitted prior to the filing of the Vegetation Management Plan, as required by 333 CMR 11.00: Rights of Way Management, on maps of a scale which will enable the issuing authority to find and delineate those Areas Subject to Protection under M.G.L. c. 131, § 40 identified in 310 CMR 10.02(1)(a) through (c) and the Buffer Zone identified in 310 CMR 10.02(2) within the vicinity of the project area.
314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth and/or is a water-dependent use project that requires a permit, license or written approval pursuant to 310 CMR 9.00: Waterways the applicant may file a Notice of Intent that is a Combined Application. In that event, an additional copy of the Combined Application shall be sent to the Department's Boston Office.
Concurrent with the filing of the Notice of Intent, the applicant shall provide notification to all Abutters. Notwithstanding the foregoing, the requirement to provide Abutter notification is subject to the following limits. An applicant is required to provide notification to an Abutter whose Lot is separated from the Project Locus by a public or private street or body of water only if the Abutter's Lot is within 100 feet from the property line of the Project Locus. An applicant who proposes work solely within Land under Water Bodies or Waterways, or solely within a Lot with an area greater than50 acres, is required to provide notification only to Abutters whose Lot is within one hundred feet from the Project Site. An applicant proposing a Linear- shaped Project greater than 1,000 feet in length is required to provide notification only to Abutters whose Lot is within 1,000 feet from the Project Site. Abutter notification is not required for projects proposed by the Massachusetts Department of Transportation Highway Division pursuant to St. 1993, c. 472 as approved on January 13, 1994. The applicant shall provide notification at the mailing addresses shown on the most recent applicable tax list from the municipal assessor. Notification shall be at the applicant's expense. The notification shall state where within the municipality copies of the Notice of Intent may be examined or obtained and where information on the date, time, and location of the public hearing may be obtained. To ensure compatibility with local procedures, applicants must comply with any rules of the local conservation commission pertaining to the location for examining or obtaining the Notice of Intent and information about the hearing. The applicant shall provide written notification to all Abutters required to be notified by hand delivery or certified mail, return receipt requested, or by certificates of mailing. Mailing at least seven days prior to the public hearing shall constitute timely notice. The applicant shall present either the certified mail receipts or certificate of mailing receipts for all Abutters at the beginning of the public hearing. The presentation of the receipts for all abutters required to be notified as identified on the tax list shall constitute compliance with Abutter notification requirements. The conservation commission shall determine whether the applicant has complied with Abutter notification requirements. The Department will dismiss Requests for Action based on allegations of failure to comply with Abutter notification requirements, absent a clear showing by an Abutter seeking Department action that the applicant failed to notify the Abutter. An applicant submitting a Notice of Intent for a project that is also subject to 310 CMR 9.00: Waterways and/or 314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth may provide joint public notice by appending to the public notice required by 310 CMR 9.13: Public Notice and Participation Requirements and/or 314 CMR 9.05: Submission of an Application, as applicable, notification that a Notice of Intent is pending before the issuing authority, provided the notification complies with 310 CMR 10.05(4). An applicant may provide a joint public notice, even if the Notice of Intent is not a Combined Application. (b) For certain purposes, other forms of Notices may be used.
Notwithstanding the foregoing, when the issuing authority has determined that an activity outside the Areas Subject to Protection under M.G.L. c. 131, § 40 and outside the Buffer Zone has in fact altered an Area Subject to Protection under M.G.L. c. 131, § 40, it may require such plans, supporting calculations and other documentation as are necessary to describe the entire activity.
Notwithstanding the provisions contained in 310 CMR 10.10, 310 CMR 10.05(4)(g) shall apply to any Notice of Intent whenever filed.
The standards and presumptions to be used by the issuing authority in determining whether an area is significant to the interests identified in M.G.L. c. 131, § 40, are found in 310 CMR 10.21 through 10.37 (for coastal wetlands) and 10.51 through 10.60 (for inland wetlands).
The Order shall impose conditions only upon work or the portion thereof that is to be undertaken within an Area Subject to Protection under M.G.L. c. 131, § 40 or within the Buffer Zone. The Order shall impose conditions to control erosion and sedimentation within resource areas and the Buffer Zone. The Order shall impose conditions setting limits on the quantity and quality of discharge from a point source (both closed and open channel), when said limits are necessary to protect the interests identified in M.G.L. c. 131, § 40; provided, however, that the point of discharge falls within an Area Subject to Protection under M.G.L. c. 131, § 40 or within the Buffer Zone, and further provided that said conditions are consistent with the limitations set forth in 310 CMR 10.03(4).
Notwithstanding the foregoing, when the issuing authority has determined that an Activity outside the Areas Subject to Protection under M.G.L. c. 131, § 40 and outside the Buffer Zone has in fact altered an Area Subject to Protection under M.G.L.c. 131,§ 40, it shall impose such conditions on any portion of the activity as are necessary to contribute to the protection of the interests identified in M.G.L.c. 131, § 40.
When the issuing authority determines that a project meets the eligibility criteria for a Restoration Order of Conditions, the issuing authority shall impose only the conditions set forth in the applicable provisions of 310 CMR 10.00 for that Restoration Order of Conditions. A Restoration Order of Conditions may reference the plans and specifications approved by the issuing authority. If the Department issues a Combined Permit, the Department may append to the Restoration Order of Conditions any conditions that the Department has authority to impose pursuant to 310 CMR 9.00: Waterways and 314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth to the extent they are applicable. The requirement that an Order shall impose conditions only upon work or the portion thereof that is to be undertaken within an Area Subject to Protection under M.G.L. c. 131, § 40, or within the Buffer Zone does not restrict the authority of the Department to append to a Combined Permit any conditions that the Department has the authority to impose under 310 CMR 9.00: Waterways and 314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth to the extent they are applicable.
This Standard is met when the stormwater management system is designed to infiltrate the required recharge volume as determined in accordance with the Massachusetts Stormwater Handbook.
Where the Department is requested to issue a Superseding Determination or Order of Conditions, the conservation commission shall be a party to all agency proceedings and hearings before the Department.
Based upon its review of the Notice of Intent, the Order, any informal meeting or site inspection, and any other additional plans, information, or documentation submitted under 310 CMR 10.05(7)(f) or (g), the Department shall issue a Superseding Order for the protection of the interests identified in M.G.L. c. 131, § 40. The Superseding Order shall impose such conditions as are necessary to meet the performance standards set forth in 310 CMR 10.21 through 10.60 and stormwater standards set forth at 301 CMR 10.05(6)(k) for the protection of those interests. The Superseding Order shall prohibit any work or any portions thereof that cannot be conditioned to protect such interests. The Department may issue a Superseding Order which affirms the Order issued by the conservation commission. The Department shall issue a Restoration Order of Conditions as the Superseding Order of Conditions in the event it determines that the project meets the eligibility criteria for a Restoration Order of Conditions. If the applicant submitted a Combined Application for a project that requires a 401 Water Quality Certification pursuant to 314 CMR 9.00: 401
Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth, or a water-dependent use project that requires a Chapter 91 license, permit or other written approval pursuant to 310 CMR 9.00: Waterways, the Department may issue a Combined Permit that serves as the Superseding Order of Conditions, the 401 Water Quality Certification, and/or the Chapter 91 permit, license or other written approval, whichever is applicable, provided the Department determines that the project meets the requirements for obtaining such Order, Certification, permit, license or other written approval.
The request for a variance shall be sent to the Department by certified mail or hand delivered and a copy thereof shall at the same time be sent by certified mail or hand delivered to the conservation commission and any other parties.
The Department will place a notice in the Environmental Monitor published by the Massachusetts Environmental Policy Act Office of the Executive Office of Energy and Environmental Affairs to solicit public comments on the request. The Department shall conduct a public hearing on a request for a variance. After reviewing the information submitted with the request for a variance and any other information submitted by any party within the public comment period, the Commissioner shall issue a decision as to whether to grant the variance. Within ten days of the date of issuance of the Commissioner's decision on the variance, any person who submitted comments during the public comment period may, according to the procedures specified in 310 CMR 10.05(7)(j), request an adjudicatory hearing on the decision. On a request for a variance based on overriding public interest, the Commissioner may dismiss the request to hold an adjudicatory hearing if the request repeats matters adequately considered in the variance decision, renews claims or arguments previously raised, or attempts to raise new claims or arguments not raised during the public comment period. On a request for a variance to avoid restrictions that would constitute an unconstitutional taking, the Commissioner shall hold an adjudicatory hearing. If an adjudicatory hearing is held, the applicant has the burden of demonstrating that the project meets the criteria necessary for a variance. Other parties to the adjudicatory hearing may introduce evidence either in favor of or opposing the request for a variance.
For projects in which all of the proposed work will be undertaken on land within the boundaries of one city or town, the request for a variance shall not be filed until the applicant first files a Notice of Intent with the Conservation Commission. The Commission shall review the project in accordance with the procedures set forth in 310 CMR 10.01 through 10.10 and issue an Order of Conditions consistent with 310 CMR 10.21 through 10.60. Within ten days of the issuance of the Order of Conditions, the applicant may request the Department to issue a Superseding Order. The Department staff shall review the project in accordance with the procedures set forth in 310 CMR 10.01 through 10.10 and shall issue a Superseding Order consistent with the provisions of 310 CMR 10.21 through 10.60. Within ten days of the issuance of the Superseding Order, the applicant may request an adjudicatory hearing on that order and/or a variance under 310 CMR 10.05(10) according to the procedure previously described.
For projects in which the proposed work will be undertaken on land within the boundaries of more than one city or town, the applicant may file a request for a variance directly with the Commissioner, with a copy to each affected conservation commission. If, after public notice, the Commissioner finds that a project meets the variance criteria, he shall specify which regulation(s) has been waived and what general requirements or conditions must be met to satisfy the variance criteria listed in 310 CMR 10.05(10)(a). The applicant shall then file a Notice of Intent with the appropriate conservation commissions in accordance with the procedures contained in 310 CMR 10.01 through 10.10. The conservation commissions shall issue Orders of Conditions consistent with all provisions of 310 CMR 10.21 through 10.60 except those waived by the Commissioner and containing any additional conditions or requirements imposed by the Commissioner in the variance. The usual procedures contained in 310 CMR 10.01 through 10.10 for requesting Superseding Orders and adjudicatory hearings remain applicable.
Commentary
310 CMR 10.05(10), which provides that the Commissioner may waive the application of one or more of the regulations on the basis of overriding public benefit is intended to be employed only in rare and unusual cases. The provision authorizing a variance request directly to the Commissioner for projects on land within more than one city or town is intended to apply to projects that involve functionally related work in several contiguous towns (e.g., transportation and energy transmission facilities) and to provide for a single uniform determination concerning alternative locations and the other variance criteria.
310 CMR, § 10.05