220 Mass. Reg. 24.08

Current through Register 1524, June 21, 2024
Section 24.08 - Long-term Contracts and RPS Requirements
(1)220 CMR 24.00 will not limit consideration of other Short- or Long-term Contracts for power and/or RECs submitted by a Distribution Company for review and approval by the Department.
(2) If a Distribution Company has entered into Long-term Contracts consistent with 220 CMR 24.00, it shall not be required by regulation or order or other agreement to enter into additional Long-term Contracts under 220 CMR 24.00; provided, however, Distribution Companies may voluntarily execute additional Long-term Contracts, subject to the approval of the Department.

220 CMR 24.08

Adopted by Mass Register Issue 1335, eff. 3/24/2017.
Amended by Mass Register Issue 1336, eff. 3/24/2017.