Documents Required To Closeout Construction of Buildings
RUS Form No. | Description | Use with | No. of copies prepared by | Distribution | |||
Contract | Force account | Contractor | Architect/engineer | Borrower | Contractor | ||
238 | Construction or Equipment Contract Amendment (if not previously submitted, send to RUS for approval) | X | (3) | (to RUS) | (to RUS) | ||
181 | Certificate of Completion (contract construction)1 | X | 2 | 1 | 1 | ||
231 | Certificate of Contractor | X | 1 | 1 | |||
224 | Waiver and Release of Lien From Each Supplier | X | 1 | 1 | |||
213 | Certificate (buy American) | X | 1 | 1 | |||
None2 | "As Built" Plans and Specifications | X | X | 1 | 1 | ||
None | Guarantees, Warranties, Bonds, Operating or Maintenance Instructions, etc | X | 1 | 1 | |||
None | Architect/Engineer seismic safety certification | X | X | 2 | 1 | 1 |
1 Cost of materials and services furnished by borrower are not to be included in Total Cost on RUS Form 181.
2 When only minor changes were made during construction, two copies of a statement to that effect from the Architect will be accepted instead of the "as built" Plans and Specifications.
7 C.F.R. §1753.30