Each closure to be installed in a pipeline system must comply with the 2007 ASME Boiler and Pressure Vessel Code (BPVC) (Section VIII, Division 1) (incorporated by reference, see§ 195.3 ) and must have pressure and temperature ratings at least equal to those of the pipe to which the closure is attached.
49 C.F.R. §195.124