48 C.F.R. § 925.103

Current through May 31, 2024
Section 925.103 - Exceptions
(b)Nonavailabilty -
(2)
(i)Individual determinations. Contracting officers may make the determination required by 48 CFR 25.103(b)(2)(i) , provided such determination is factually supported in writing. If the contract is estimated to exceed $1 million, the Head of the Contracting Activity must approve the determination.
(ii) Proposals to add an article to the list of nonavailable articles at 48 CFR 25.104 , with appropriate justifications, must be submitted for approval by the Senior Procurement Executive and submission to the appropriate council.

48 C.F.R. §925.103

74 FR 36366, July 22, 2009, as amended at 75 FR 69013, Nov. 10, 2010; 81 FR 45977, July 15, 2016