48 C.F.R. § 843.205

Current through October 31, 2024
Section 843.205 - Contract clauses

As authorized in the introductory text of clauses FAR 52.243-1, Changes-Fixed-Price; FAR 52.243-2, Changes-Cost-Reimbursement; and FAR 52.243-4, Changes, and in the prescription at FAR 43.205(c) for FAR 52.243-3, Changes-Time-and-Materials or Labor-Hours, the contracting officer may vary the period within which a contractor must assert its right to an equitable adjustment but the extended period shall not exceed 60 calendar days.

48 C.F.R. §843.205

84 FR 45682 , 9/30/2019