48 C.F.R. §§ 734.002-70

Current through May 31, 2024
Section 734.002-70 - USAID policy

In order for an USAID acquisition to be considered a major system acquisition it must meet the criteria of OMB Circular A-109 and FAR part 34, and must have an estimated value of $15 million or more during the first year of the contract. All major systems acquisition must be approved in advance by the M/OAA Director.

48 C.F.R. §§734.002-70

55 FR 39976, Oct. 1, 1990, as amended at 64 FR 42040, Aug. 3, 1999; 72 FR 19670, Apr. 19, 2007