48 C.F.R. §§ 452.246-70

Current through May 31, 2024
Section 452.246-70 - Inspection and Acceptance

As prescribed in 446.370, insert the following clause:

Inspection and Acceptance (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at: ______.*

(End of clause)

* Contracting Officer shall insert appropriate identifying data.

Alternate I (FEB 1988). As prescribed in 446.370, substitute a paragraph (b) and add a paragraph (c):

(b) Inspection will be performed at: ______.*
(c) Acceptance will be performed at: ______.*

(End of clause)

48 C.F.R. §§452.246-70