48 C.F.R. §§ 252.232-7018

Current through September 30, 2024
Section 252.232-7018 - Progress Payments-Multiple Lots

As prescribed in 232.502-4-70(c), use the following clause:

Progress Payments-Multiple Lots (MAY 2023)

(a)Definitions. As used in this clause-

Lot means one or more fixed-price deliverable line items or deliverable subline items representing a single, severable group where the sum of the costs for each group is segregated and a single progress payment rate is used.

Multiple lots means more than one lot on a single contract where progress payment proration is performed on a lot-wide, versus contract-wide, basis.

(b) When submitting progress payment requests under the billing instructions in Federal Acquisition Regulation (FAR) clause 52.232-16, Progress Payments, or Defense Federal Acquisition Regulation Supplement (DFARS) clause 252.232-7002, Progress Payments for Foreign Military Sales Acquisitions, of this contract, the Contractor shall-
(1) Submit separate progress payment requests for each lot identified in the contract;
(2) Identify the contract price for the lot as the sum of all fixed-priced line items identified to the lot, in accordance with FAR 32.501-3;
(3) Identify the lot on each progress payment request to which the request applies;
(4) Calculate each request on the basis of the price, costs (including the cost to complete), subcontractor financing, and progress payment liquidations of the lot to which it applies; and
(5) Distribute costs among lots in a manner acceptable to the Administrative Contracting Officer.
(c) Submit a separate progress payment request for U.S. and FMS requirements in accordance with the DFARS clause 252.232-7002, Progress Payments for Foreign Military Sales Acquisitions, of this contract.

(End of clause)

48 C.F.R. §§252.232-7018

88 FR 33833, May 25, 2023
88 FR 33833, 5/25/2023