48 C.F.R. §§ 228.102-1

Current through September 30, 2024
Section 228.102-1 - General

The requirement for performance and payment bonds is waived for cost-reimbursement contracts. However, for cost-type contracts with fixed-price construction subcontracts over $40,000, require the prime contractor to obtain from each of its construction subcontractors performance and payment protections in favor of the prime contractor as follows:

(1) For fixed-price construction subcontracts over $40,000, but not exceeding $150,000, payment protection sufficient to pay labor and material costs, using any of the alternatives listed at FAR 28.102-1(b)(1).
(2) For fixed-price construction subcontracts over $150,000-
(i) A payment bond sufficient to pay labor and material costs; and
(ii) A performance bond in an equal amount if available at no additional cost.

48 C.F.R. §§228.102-1

68 FR 36945, June 20, 2003, as amended at 71 FR 75892, Dec. 19, 2006; 75 FR 45074, Aug. 2, 2010; 80 FR 36904, June 26, 2015; 85 FR 61504, Sept. 29, 2020
85 FR 61504, 9/29/2020