48 C.F.R. §§ 204.470-3

Current through September 30, 2024
Section 204.470-3 - Contract clause

Use the clause at 252.204-7010, Requirement for Contractor to Notify DoD if the Contractor's Activities are Subject to Reporting Under the U.S.-International Atomic Energy Agency Additional Protocol, in solicitations and contracts for research and development or major defense acquisition programs involving-

(a) Any fissionable materials (e.g., uranium, plutonium, neptunium, thorium, americium);
(b) Other radiological source materials; or
(c) Technologies directly related to nuclear power production, including nuclear or radiological waste materials.

48 C.F.R. §§204.470-3

74 FR 2412, Jan. 15, 2009