48 C.F.R. § 1843.205

Current through May 31, 2024
Section 1843.205 - Contract clauses

As authorized in the prefaces of clauses FAR 52.243-1, Changes-Fixed Price; FAR 52.243-2, Changes-Cost Reimbursement; and FAR 52.243-4, Changes; and in the prescription at 43.205(c) for FAR 52.243-3, Changes-Time-and-Material or Labor-Hours, the period within which a contractor must assert its right to an equitable adjustment may be varied not to exceed 60 calendar days.

48 C.F.R. §1843.205

65 FR 58932, Oct. 3, 2000