48 C.F.R. § 1842.7201

Current through May 31, 2024
Section 1842.7201 - General
(a) [Reserved]
(b) Reporting requirements.
(1) Use of the NASA Contractor Financial Management Reports, the NASA form 533 series, is required on cost-type, price redetermination, and fixed-price incentive contracts when the following dollar, period of performance, and scope criteria are met:

Contract value/scopePeriod of performance533M533Q
$500K to $999K1 year or moreRequiredOptional.
$1,000,000 and overLess than 1 yearRequiredOptional.
$1,000,000 and over1 year or moreRequiredRequired.

(2) When it is probable that a contract will ultimately meet the criteria in paragraph (b)(1) of this section through change orders, supplemental agreements, etc., the reporting requirement must be implemented in the contract based on the estimated final contract value at the time of award.

48 C.F.R. §1842.7201

62 FR 14017, Mar. 25, 1997, as amended at 69 FR 44609, July 27, 2004