(i) Example 1-New E.O. wage rate is $16.10. | |
Previous E.O. wage rate is $15.70. The current service or construction wage determination rate applicable to this worker under the contract is $15.75. | Analysis: The calculation is $16.10-$15.80 = $.30. The price adjustment for this worker is $.30. |
The actual wage currently paid to the worker is $15.80. | |
(ii) Example 2-New E.O. wage rate is $15.50. | |
Previous E.O. wage rate is $15.10. The current service or construction wage determination rate applicable to this worker under the contract is $15.75. | Analysis: The calculation is $15.50-$15.80 = -$.30. There is no price adjustment for this worker. |
The actual wage currently paid to the worker is $15.80. |
48 C.F.R. §22.1904