Current through November 30, 2024
Section 4.804-2 - Closeout of the contracting office files if another office administers the contract(a) Contract files for contracts using simplified acquisition procedures should be considered closed when the contracting officer receives evidence of receipt of property and final payment, unless otherwise specified by agency regulation.(b) All other contract files shall be closed as soon as practicable after the contracting officer receives a contract completion statement from the contract administration office. The contracting officer shall ensure that all contractual actions required have been completed and shall prepare a statement to that effect. This statement is authority to close the contract file and shall be made a part of the official contract file.48 FR 42113, Sept. 19, 1983, as amended at 60 FR 34746, July 3, 1995