45 C.F.R. § 2102.13

Current through September 30, 2024
Section 2102.13 - Project eligibility criteria for placement on a Consent Calendar

With respect to submissions to the Commission for projects that meet the following criteria, the Secretary, at his/her discretion and in coordination with the Commission's staff, may place these projects on a Consent Calendar according to § 2102.14 .

(a) Additions to buildings of less than 25 percent (%) of the original structure and no more than 25,000 sq. ft.;
(b) New construction of less than 25,000 sq. ft.;
(c) Window replacement projects;
(d) Cellular or other communications antenna installations or replacements;
(e) New or replacement signs;
(f) Cleaning, routine maintenance, repairs or replacement-in-kind of exterior finish materials;
(g) Temporary utility or construction structures;
(h) And does not include new physical perimeter security items.

45 C.F.R. §2102.13

70 FR 49194, Aug. 23, 2005