Current through November 30, 2024
Section 3264.12 - What must I submit to BLM after I abandon a well?Send us a well abandonment report within 30 days after you abandon a well. If you plan to restore the site at a later date, you may submit a separate report within 30 days after completing site restoration. The well abandonment report must contain:
(a) A complete chronology of all work done;(b) A description of each plug, including:(1) Type and amount of cement used;(2) Depth that the drill pipe or tubing was run to set the plug;(3) Depth to top of plug; and(4) If the plug was verified, whether it was done by tagging or pressure testing; and(c) A description of surface restoration procedures.