43 C.F.R. § 3179.101

Current through May 31, 2024
Section 3179.101 - [Effective until 6/10/2024] Initial production testing
(a) Gas flared during the initial production test of each completed interval in a well is royalty free until one of the following occurs:
(1) The operator determines that it has obtained adequate reservoir information;
(2) Thirty (30) days have passed since the beginning of the production test, unless the BLM approves a longer test period; or
(3) The operator has flared 50 million cubic feet (MMcf) of gas.
(b) The operator may request a longer test period and must submit its request using a Sundry Notice.

43 C.F.R. §3179.101

81 FR 83078, 1/17/2017; 82 FR 58072, 1/8/2018; 83 FR 49211, 11/27/2018