Current through November 30, 2024
Section 50-201.201 - Breach of stipulations(a) Whenever the Department of Labor notifies the head of a contracting agency that a contractor is liable for liquidated damages by reason of a breach of stipulations as provided in section 2 of the act, there shall be withheld from any balance due under the contract such amount as may be necessary to satisfy such liability pending final disposition of the case.(b) Whenever a final determination of a breach of stipulations is made, the Secretary of Labor will furnish to the contracting agency a copy of the findings and decision with such recommendations as will assist the contracting agency in determining whether or not the contract should be canceled for such breach.Regs. 504, 1 FR 1627, Sept. 19, 1936. Redesignated at 24 FR 10952, Dec. 30, 1959