Current through November 30, 2024
Section 70.5 - Permit applications(a)Duty to apply. For each part 70 source, the owner or operator shall submit a timely and complete permit application in accordance with this section. (1)Timely application.(i) A timely application for a source applying for a part 70 permit for the first time is one that is submitted within 12 months after the source becomes subject to the permit program or on or before such earlier date as the permitting authority may establish.(ii) Part 70 sources required to meet the requirements under section 112(g) of the Act, or to have a permit under the preconstruction review program approved into the applicable implementation plan under part C or D of title I of the Act, shall file a complete application to obtain the part 70 permit or permit revision within 12 months after commencing operation or on or before such earlier date as the permitting authority may establish. Where an existing part 70 permit would prohibit such construction or change in operation, the source must obtain a permit revision before commencing operation.(iii) For purposes of permit renewal, a timely application is one that is submitted at least 6 months prior to the date of permit expiration, or such other longer time as may be approved by the Administrator that ensures that the term of the permit will not expire before the permit is renewed. In no event shall this time be greater than 18 months.(iv) Applications for initial phase II acid rain permits shall be submitted to the permitting authority by January 1, 1996 for sulfur dioxide, and by January 1, 1998 for nitrogen oxides.(2)Complete application. The program shall provide criteria and procedures for determining in a timely fashion when applications are complete. To be deemed complete, an application must provide all information required pursuant to paragraph (c) of this section, except that applications for permit revision need supply such information only if it is related to the proposed change. Information required under paragraph (c) of this section must be sufficient to evaluate the subject source and its application and to determine all applicable requirements. The program shall require that a responsible official certify the submitted information consistent with paragraph (d) of this section. Unless the permitting authority determines that an application is not complete within 60 days of receipt of the application, such application shall be deemed to be complete, except as otherwise provided in § 70.7(a)(4) of this part. If, while processing an application that has been determined or deemed to be complete, the permitting authority determines that additional information is necessary to evaluate or take final action on that application, it may request such information in writing and set a reasonable deadline for a response. The source's ability to operate without a permit, as set forth in § 70.7(b) of this part, shall be in effect from the date the application is determined or deemed to be complete until the final permit is issued, provided that the applicant submits any requested additional information by the deadline specified by the permitting authority.(3)Confidential information. In the case where a source has submitted information to the State under a claim of confidentiality, the permitting authority may also require the source to submit a copy of such information directly to the Administrator.(b)Duty to supplement or correct application. Any applicant who fails to submit any relevant facts or who has submitted incorrect information in a permit application shall, upon becoming aware of such failure or incorrect submittal, promptly submit such supplementary facts or corrected information. In addition, an applicant shall provide additional information as necessary to address any requirements that become applicable to the source after the date it filed a complete application but prior to release of a draft permit.(c)Standard application form and required information. The State program under this part shall provide for a standard application form or forms. Information as described below for each emissions unit at a part 70 source shall be included in the application. The Administrator may approve as part of a State program a list of insignificant activities and emissions levels which need not be included in permit applications. However, for insignificant activities which are exempted because of size or production rate, a list of such insignificant activities must be included in the application. An application may not omit information needed to determine the applicability of, or to impose, any applicable requirement, or to evaluate the fee amount required under the schedule approved pursuant to § 70.9 of this part. The permitting authority may use discretion in developing application forms that best meet program needs and administrative efficiency. The forms and attachments chosen, however, shall include the elements specified below: (1) Identifying information, including company name and address (or plant name and address if different from the company name), owner's name and agent, and telephone number and names of plant site manager/contact.(2) A description of the source's processes and products (by Standard Industrial Classification (SIC) Code) including those associated with any proposed AOS identified by the source.(3) The following emission-related information:(i) All emissions of pollutants for which the source is major, and all emissions of regulated air pollutants. A permit application shall describe all emissions of regulated air pollutants emitted from any emissions unit, except where such units are exempted under this paragraph (c) of this section. The permitting authority shall require additional information related to the emissions of air pollutants sufficient to verify which requirements are applicable to the source, and other information necessary to collect any permit fees owed under the fee schedule approved pursuant to § 70.9(b) of this part.(ii) Identification and description of all points of emissions described in paragraph (c)(3)(i) of this section in sufficient detail to establish the basis for fees and applicability of requirements of the Act.(iii) Emissions rate in tpy and in such terms as are necessary to establish compliance consistent with the applicable standard reference test method. For emissions units subject to an annual emissions cap, tpy can be reported as part of the aggregate emissions associated with the cap, except where more specific information is needed, including where necessary to determine and/or assure compliance with an applicable requirement.(iv) The following information to the extent it is needed to determine or regulate emissions: Fuels, fuel use, raw materials, production rates, and operating schedules.(v) Identification and description of air pollution control equipment and compliance monitoring devices or activities.(vi) Limitations on source operation affecting emissions or any work practice standards, where applicable, for all regulated pollutants at the part 70 source.(vii) Other information required by any applicable requirement (including information related to stack height limitations developed pursuant to section 123 of the Act).(viii) Calculations on which the information in paragraphs (c)(3 (i) through (vii) of this section is based.(4) The following air pollution control requirements:(i) Citation and description of all applicable requirements, and(ii) Description of or reference to any applicable test method for determining compliance with each applicable requirement.(5) Other specific information that may be necessary to implement and enforce other applicable requirements of the Act or of this part or to determine the applicability of such requirements.(6) An explanation of any proposed exemptions from otherwise applicable requirements.(7) Additional information as determined to be necessary by the permitting authority to define proposed AOSs identified by the source pursuant to § 70.6(a)(9) of this part or to define permit terms and conditions implementing any AOS under § 70.6(a)(9) or implementing § 70.4(b)(12) or § 70.6(a)(10) of this part. The permit application shall include documentation demonstrating that the source has obtained all authorization(s) required under the applicable requirements relevant to any proposed AOSs, or a certification that the source has submitted all relevant materials to the appropriate permitting authority for obtaining such authorization(s).(8) A compliance plan for all part 70 sources that contains all the following: (i) A description of the compliance status of the source with respect to all applicable requirements.(ii) A description as follows: (A) For applicable requirements with which the source is in compliance, a statement that the source will continue to comply with such requirements.(B) For applicable requirements that will become effective during the permit term, a statement that the source will meet such requirements on a timely basis.(C) For requirements for which the source is not in compliance at the time or permit issuance, a narrative description of how the source will achieve compliance with such requirements.(D) For applicable requirements associated with a proposed AOS, a statement that the source will meet such requirements upon implementation of the AOS. If a proposed AOS would implicate an applicable requirement that will become effective during the permit term, a statement that the source will meet such requirements on a timely basis.(iii) A compliance schedule as follows: (A) For applicable requirements with which the source is in compliance, a statement that the source will continue to comply with such requirements.(B) For applicable requirements that will become effective during the permit term, a statement that the source will meet such requirements on a timely basis. A statement that the source will meet in a timely manner applicable requirements that become effective during the permit term shall satisfy this provision, unless a more detailed schedule is expressly required by the applicable requirement.(C) A schedule of compliance for sources that are not in compliance with all applicable requirements at the time of permit issuance. Such a schedule shall include a schedule of remedial measures, including an enforceable sequence of actions with milestones, leading to compliance with any applicable requirements for which the source will be in noncompliance at the time of permit issuance. This compliance schedule shall resemble and be at least as stringent as that contained in any judicial consent decree or administrative order to which the source is subject. Any such schedule of compliance shall be supplemental to, and shall not sanction noncompliance with, the applicable requirements on which it is based.(D) For applicable requirements associated with a proposed AOS, a statement that the source will meet such requirements upon implementation of the AOS. If a proposed AOS would implicate an applicable requirement that will become effective during the permit term, a statement that the source will meet such requirements on a timely basis. A statement that the source will meet in a timely manner applicable requirements that become effective during the permit term will satisfy this provision, unless a more detailed schedule is expressly required by the applicable requirement.(iv) A schedule for submission of certified progress reports no less frequently than every 6 months for sources required to have a schedule of compliance to remedy a violation.(v) The compliance plan content requirements specified in this paragraph shall apply and be included in the acid rain portion of a compliance plan for an affected source, except as specifically superseded by regulations promulgated under title IV of the Act with regard to the schedule and method(s) the source will use to achieve compliance with the acid rain emissions limitations.(9) Requirements for compliance certification, including the following:(i) A certification of compliance with all applicable requirements by a responsible official consistent with paragraph (d) of this section and section 114(a)(3) of the Act;(ii) A statement of methods used for determining compliance, including a description of monitoring, recordkeeping, and reporting requirements and test methods;(iii) A schedule for submission of compliance certifications during the permit term, to be submitted no less frequently than annually, or more frequently if specified by the underlying applicable requirement or by the permitting authority; and(iv) A statement indicating the source's compliance status with any applicable enhanced monitoring and compliance certification requirements of the Act.(10) The use of nationally-standardized forms for acid rain portions of permit applications and compliance plans, as required by regulations promulgated under title IV of the Act.(d) Any application form, report, or compliance certification submitted pursuant to these regulations shall contain certification by a responsible official of truth, accuracy, and completeness. This certification and any other certification required under this part shall state that, based on information and belief formed after reasonable inquiry, the statements and information in the document are true, accurate, and complete.57 FR 32295, July 21, 1992, as amended at 74 FR 51438 , Oct. 6, 2009