40 C.F.R. § 68.77

Current through May 31, 2024
Section 68.77 - Pre-startup review
(a) The owner or operator shall perform a pre-startup safety review for new stationary sources and for modified stationary sources when the modification is significant enough to require a change in the process safety information.
(b) The pre-startup safety review shall confirm that prior to the introduction of regulated substances to a process:
(1) Construction and equipment is in accordance with design specifications;
(2) Safety, operating, maintenance, and emergency procedures are in place and are adequate;
(3) For new stationary sources, a process hazard analysis has been performed and recommendations have been resolved or implemented before startup; and modified stationary sources meet the requirements contained in management of change, § 68.75 .
(4) Training of each employee involved in operating a process has been completed.

40 C.F.R. § 68.77