As stated in § 63.8826 , you must comply with the applicable General Provisions requirements according to the following table:
Citation | Requirement | Applies to subpart MMMMM | Explanation |
§ 63.1 | Initial applicability determination; applicability after standard established; permit requirements; extensions; notifications | Yes | |
§ 63.2 | Definitions | Yes | Additional definitions are found in § 63.8830 . |
§ 63.3 | Units and abbreviations | Yes | |
§ 63.4 | Prohibited activities; compliance date; circumvention, severability | Yes | |
§ 63.5 | Construction/reconstruction applicability; applications; approvals | Yes | |
§ 63.6(a) | Compliance with standards and maintenance requirements-applicability | Yes | |
§ 63.6(b)(1)-(4) | Compliance dates for new or reconstructed sources | Yes | § 63.8786 specifies compliance dates. |
§ 63.6(b)(5) | Notification if commenced construction or reconstruction after proposal | Yes | |
§ 63.6(b)(6) | [Reserved] | Yes | |
§ 63.6(b)(7) | Compliance dates for new or reconstructed area sources that become major | Yes | § 63.8786 specifies compliance dates. |
§ 63.6(c)(1)-(2) | Compliance dates for existing sources | Yes | § 63.8786 specifies compliance dates. |
§ 63.6(c)(3)-(4) | [Reserved] | Yes | |
§ 63.6(c)(5) | Compliance dates for existing area sources that become major | Yes | § 63.8786 specifies compliance dates. |
§ 63.6(d) | [Reserved] | Yes | |
§ 63.6(e)(1)(i) | General duty to minimize emissions | No | § 63.8794(c) specifies general duty requirements. |
§ 63.6(e)(1)(ii) | Requirement to correct malfunctions as soon as possible | No | |
§ 63.6(e)(1)(iii) | Enforceability of requirements independent of other regulations | Yes | |
§ 63.6(e)(2) | [Reserved] | Yes | |
§ 63.6(e)(3) | SSM plans | No | |
§ 63.6(f)(1) | Compliance except during SSM | No | |
§ 63.6(f)(2)-(3) | Methods for determining compliance | Yes | |
§ 63.6(g) | Use of an alternative nonopacity emission standard | Yes | |
§ 63.6(h) | Compliance with opacity/visible emission standards | No | Subpart MMMMM does not specify opacity or visible emission standards. |
§ 63.6(i) | Extension of compliance with emission standards | Yes | |
§ 63.6(j) | Presidential compliance exemption | Yes | |
§ 63.7(a)(1)-(2) | Performance test dates | Yes | Except for loop slitter affected sources as specified in § 63.8798(a) . |
§ 63.7(a)(3) | Administrator's section 114 authority to require a performance test | Yes | |
§ 63.7(b) | Notification of performance test and rescheduling | Yes | |
§ 63.7(c) | Quality assurance program and site-specific test plans | Yes | |
§ 63.7(d) | Performance testing facilities | Yes | |
§ 63.7(e)(1) | Conditions for conducting performance tests | No | Requirements for performance test conditions are found in § 63.8800(b) and (c) . |
§ 63.7(e)(2)-(3) | Performance test data reduction and number of test runs | Yes | |
§ 63.7(f) | Use of an alternative test method | Yes | |
§ 63.7(g) | Performance test data analysis, recordkeeping, and reporting | Yes | |
§ 63.7(h) | Waiver of performance tests | Yes | |
§ 63.8(a)(1)-(2) | Applicability of monitoring requirements | Yes | Unless otherwise specified, all of § 63.8 applies only to new or reconstructed flame lamination sources. Additional monitoring requirements for these sources are found in §§ 63.8794(f) and (g) and 63.8804 . |
§ 63.8(a)(3) | [Reserved] | Yes | |
§ 63.8(a)(4) | Monitoring with flares | No | Subpart MMMMM does not refer directly or indirectly to § 63.11 . |
§ 63.8(b) | Conduct of monitoring and procedures when there are multiple effluents and multiple monitoring systems | Yes | |
§ 63.8(c)(1)-(3) | Continuous monitoring system (CMS) operation and maintenance | No | CMS requirements are found in § 63.8794(f) and (g) . |
§ 63.8(c)(4) | Continuous monitoring system requirements during breakdown, out-of-control, repair, maintenance, and high-level calibration drifts | Yes | Applies as modified by § 63.8794(g) . |
§ 63.8(c)(5) | Continuous opacity monitoring system (COMS) minimum procedures | No | Subpart MMMMM does not have opacity or visible emission standards. |
§ 63.8(c)(6) | Zero and high-level calibration checks | Yes | Applies as modified by § 63.8794(f) . |
§ 63.8(c)(7)-(8) | Out-of-control periods, including reporting | Yes | |
§ 63.8(d)-(e) | Quality control program and CMS performance evaluation | No | CMS requirements are found in § 63.8794(f) and (g) . |
§ 63.8(f)(1)-(5) | Use of an alternative monitoring method | Yes | |
§ 63.8(f)(6) | Alternative to relative accuracy test | No | Only applies to sources that use continuous emissions monitoring systems (CEMS). |
§ 63.8(g) | Data reduction | Yes | Applies as modified by § 63.8794(g) . |
§ 63.9(a) | Notification requirements-applicability | Yes | |
§ 63.9(b) | Initial notifications | Yes | Except § 63.8816(c) requires new or reconstructed affected sources to submit the application for construction or reconstruction required by § 63.9(b)(1)(iii) in lieu of the initial notification. |
§ 63.9(c) | Request for compliance extension | Yes | |
§ 63.9(d) | Notification that a new source is subject to special compliance requirements | Yes | |
§ 63.9(e) | Notification of performance test | Yes | |
§ 63.9(f) | Notification of visible emissions/opacity test | No | Subpart MMMMM does not have opacity or visible emission standards. |
§ 63.9(g)(1) | Additional CMS notifications-date of CMS performance evaluation | Yes | |
§ 63.9(g)(2) | Use of COMS data | No | Subpart MMMMM does not require the use of COMS. |
§ 63.9(g)(3) | Alternative to relative accuracy testing | No | Applies only to sources with CEMS. |
§ 63.9(h) | Notification of compliance status | Yes | |
§ 63.9(i) | Adjustment of submittal deadlines | Yes | |
§ 63.9(j) | Change in previous information | Yes | |
§ 63.9(k) | Electronic reporting procedures | Yes | Only as specified in § 63.9(j) . |
§ 63.10(a) | Recordkeeping/reporting applicability | Yes | |
§ 63.10(b)(1) | General recordkeeping requirements | Yes | §§ 63.8820 and 63.8822 specify additional recordkeeping requirements. |
§ 63.10(b)(2)(i) and (ii) | Records related to SSM periods and CMS | No | See § 63.8820 for recordkeeping of (1) date, time, and duration; (2) listing of affected source or equipment, and an estimate of the quantity of each regulated pollutant emitted over the standard; and (3) actions to minimize emissions and correct the failure. |
§ 63.10(b)(2)(iii) | Records of maintenance on air pollution control equipment. | Yes | |
§ 63.10(b)(2)(iv) and (v) | Records related to SSM | No | |
§ 63.10(b)(2)(vi)-(xi) | Records of CMS and other compliance records | Yes | |
§ 63.10(b)(2)(xii) | Records when under waiver | Yes | |
§ 63.10(b)(2) (xiii) | Records when using alternative to relative accuracy test | No | Applies only to sources with CEMS. |
§ 63.10(b)(2)(xiv) | All documentation supporting initial notification and notification of compliance status | Yes | |
§ 63.10(b)(3) | Recordkeeping requirements for applicability determinations | Yes | |
§ 63.10(c) | Additional recordkeeping requirements for sources with CMS | Yes | Applies as modified by § 63.8794(g) . |
§ 63.10(d)(1) | General reporting requirements | Yes | § 63.8818 specifies additional reporting requirements. |
§ 63.10(d)(2) | Performance test results | Yes | |
§ 63.10(d)(3) | Opacity or visible emissions observations | No | Subpart MMMMM does not specify opacity or visible emission standards. |
§ 63.10(d)(4) | Progress reports for sources with compliance extensions | Yes | |
§ 63.10(d)(5) | SSM reports | No | |
§ 63.10(e)(1) | Additional CMS reports-general | Yes | Applies as modified by § 63.8794(g) . |
§ 63.10(e)(2)(i) | Results of CMS performance evaluations | Yes | Applies as modified by § 63.8794(g) . |
§ 63.10(e)(2) | Results of continuous opacity monitoring systems performance evaluations | No | Subpart MMMMM does require the use of COMS. |
§ 63.10(e)(3) | Excess emissions/CMS performance reports | Yes | Only applies to new or reconstructed flame lamination affected sources. |
§ 63.10(e)(4) | Continuous opacity monitoring system data reports | No | Subpart MMMMM does not require the use of COMS. |
§ 63.10(f) | Recordkeeping/reporting waiver | Yes | |
§ 63.11 | Control device requirements-applicability | No | Facilities subject to subpart MMMMM do not use flares as control devices. |
§ 63.12 | State authority and delegations | Yes | § 63.8828 lists those sections of subparts MMMMM and A that are not delegated. |
§ 63.13 | Addresses | Yes | |
§ 63.14 | Incorporation by reference | Yes | Subpart MMMMM does not incorporate any material by reference. |
§ 63.15 | Availability of information/confidentiality. | Yes |
40 C.F.R. 63.1662-63 app Table 7 to Subpart MMMMM of Part 63