As stated in § 63.8545 , you must meet each compliance date in the following table that applies to you:
If you have a(n) . . . | Then you must . . . | No later than . . . |
1. New or reconstructed affected source and the initial startup of your affected source is after December 18, 2014, but before December 28, 2015 | Comply with the applicable emission limitations and work practice standards in Tables 1, 2, and 3 to this subpart | December 28, 2015. |
2. New or reconstructed affected source and the initial startup of your affected source is after December 28, 2015 | Comply with the applicable emission limitations and work practice standards in Tables 1, 2, and 3 to this subpart | Initial startup of your affected source. |
3. Existing affected source | Comply with the applicable emission limitations and work practice standards in Tables 1, 2, and 3 to this subpart | December 26, 2018. |
4. Existing area source that increases its emissions or its potential to emit such that it becomes a major source of HAP by adding a new affected source or by reconstructing | Be in compliance with this subpart | Initial startup of your affected source as a major source. |
5. New area source (i.e., an area source for which construction or reconstruction commenced after December 18, 2014) that increases its emissions or its potential to emit such that it becomes a major source of HAP | Be in compliance with this subpart | Initial startup of your affected source as a major source. |
40 C.F.R. 63.1662-63 app Table 8 to Subpart KKKKK of Part 63