As required in § 63.8075(a) and (b) , you must submit each report that applies to you on the schedule shown in the following table:
You must submit a . . . | The report must contain . . . | You must submit the report . . . |
1. Precompliance report | The information specified in § 63.8075(c) | At least 6 months prior to the compliance date; or for new sources, with the application for approval of construction or reconstruction. |
2. Notification of compliance status report | The information specified in § 63.8075(d) | No later than 150 days after the compliance date specified in § 63.7995 . |
3. Compliance report | The information specified in § 63.8075(e) | Semiannually according to the requirements in § 63.8075(b) . |
4. Performance test report | The information specified in § 63.8075(f) | Within 60 days after completing each performance test according to the requirements in § 63.8075(f) . |
5. Performance evaluation report | The information specified in § 63.8075(g) | Within 60 days after completing each CMS performance evaluation according to the requirements in § 63.8075(g) . |
40 C.F.R. 63.1662-63 app Table 9 to Subpart HHHHH of Part 63