Table 1 to § 63.2833 -Categorizing Your Source as Existing or New
If your affected source. . . | And if. . . | Then your affected source. . . |
(1) was constructed or began construction before May 26, 2000 | reconstruction has not occurred | is an existing source. |
(2) began reconstruction, as defined in § 63.2 , on or after May 26, 2000 | (i) reconstruction was part of a scheduled plan to comply with the existing source requirements of this subpart; and (ii) reconstruction was completed no later than 3 years after the effective date of this subpart | remains an existing source. |
(3) began a significant modification, as defined in § 63.2872 , at any time on an existing source | the modification does not constitute reconstruction | remains an existing source. |
(4) began a significant modification, as defined in § 63.2872 , at any time on a new source | the modification does not constitute reconstruction | remains a new source. |
(5) began reconstruction on or after May 26, 2000 | reconstruction was completed later than 3 years after the effective date of this subpart | is a new source |
(6) began construction on or after May 26, 2000 | is a new source. |