40 C.F.R. § 63.11083

Current through May 31, 2024
Section 63.11083 - [Effective 7/8/2024] When do I have to comply with this subpart?
(a) Except as specified in paragraphs (d) and (e) of this section, if you have a new or reconstructed affected source, you must comply with this subpart according to paragraphs (a)(1) and (2) of this section.
(1) If you start up your affected source before January 10, 2008, you must comply with the standards in this subpart no later than January 10, 2008.
(2) If you start up your affected source after January 10, 2008, you must comply with the standards in this subpart upon startup of your affected source.
(b) Except as specified in paragraphs (d) and (e) of this section, if you have an existing affected source, you must comply with the standards in this subpart no later than January 10, 2011.
(c) If you have an existing affected source that becomes subject to the control requirements in this subpart because of an increase in the daily throughput, as specified in § 63.11086(a) or in option 1 of table 2 to this subpart, you must comply with the standards in this subpart no later than 3 years after the affected source becomes subject to the control requirements in this subpart.
(d) All affected sources that commenced construction or reconstruction on or before June 10, 2022, must comply with the requirements in paragraphs (d)(1) through (5) of this section upon startup or on May 8, 2027, whichever is later. All affected sources that commenced construction or reconstruction after June 10, 2022, must comply with the requirements in paragraphs (d)(1) through (5) of this section upon startup, or on July 8, 2024, whichever is later.
(1) For bulk gasoline plants, the requirements specified in § 63.11086(a)(4) through (6) .
(2) For storage vessels at bulk gasoline terminals, pipeline breakout stations, or pipeline pumping stations, the requirements specified in items 1(b), 2(c), and 2(f) in table 1 to this subpart and §§ 63.11087(g) and 63.11092(f)(1)(ii) .
(3) For loading racks at bulk gasoline terminals, the requirements specified in items 1(c), 1(f), and 2(c) in table 2 to this subpart.
(4) For equipment leak inspections at bulk gasoline terminals, bulk gasoline plants, pipeline breakout stations, or pipeline pumping stations, the requirements in § 63.11089(c) .
(5) For gasoline cargo tanks, the requirements specified in § 63.11092(g)(1)(ii) .
(e) All affected sources that commenced construction or reconstruction on or before June 10, 2022, must comply with the requirements specified in items 2(d) and 2(e) in table 1 to this subpart upon startup or the next time the storage vessel is completely emptied and degassed, or by May 8, 2034, whichever occurs first. All affected sources that commenced construction or reconstruction after June 10, 2022, must comply with the requirements specified in items 2(d) and 2(e) in table 1 to this subpart upon startup, or on July 8, 2024, whichever is later.

40 C.F.R. §63.11083

73 FR 1933, Jan. 10, 2008, as amended at 76 FR 4177, Jan. 24, 2011
89 FR 39373, 7/8/2024