Section 63.7114 - How do I demonstrate initial compliance with the emission limitations standard?
(a) You must demonstrate initial compliance with each emission limit in Table 1 to this subpart that applies to you, according to Table 4 to this subpart. For existing lime kilns and their associated coolers, you may perform VE measurements in accordance with EPA Method 9 of appendix A to part 60 in lieu of installing a COMS or PM detector if any of the conditions in paragraphs (a)(1) through (3) of this section exist:
(1) You use a FF for PM control, and the FF is under positive pressure and has multiple stacks; or
(2) The control device exhausts through a monovent; or
(3) The installation of a COMS in accordance with PS-1 of appendix B to part 60 is infeasible.
(b) You must establish each site-specific operating limit in Table 3 to this subpart that applies to you according to the requirements in § 63.7112(j) and Table 5 to this subpart. Alternative parameters may be monitored if approval is obtained according to the procedures in § 63.8(f) .
(c) You must submit the Notification of Compliance Status containing the results of the initial compliance demonstration according to the requirements in § 63.7130(e) .