Table 1a-Cross Reference a b
Status | Standardc | Compliance provisionsd-§ 60.713 |
A. Coating operation alone: | ||
New | § 60.712(a) : Recover or destroy at least 93 percent of the VOC applied | (b)(1), (b)(2), (b)(3), (b)(4), (b)(5), (c), (d) |
Modified or reconstructed: | ||
1. If at least 90 percent of the VOC applied is recovered or destroyed prior to modification/reconstruction | § 60.712(b)(1) : (i) Maintain demonstrated level of VOC control or 93 percent, whichever is lower (ii) If the VOC control device is subsequently replaced, the new control device must be at least 95 percent efficient, a demonstration must be made that the overall level of VOC control is at least as high as required with the old control device (90 to 93 percent) and, if the demonstrated level is higher than the old level, maintain the higher level of control (up to 93 percent) | (a)(1), (a)(3), (b)(1), (b)(2), (b)(3), (b)(4), (c), (d) |
2. If existing coating operation has a total enclosure vented to a control device that is at least 92 percent efficient | § 60.712(b)(2) : (i) Continue to vent all VOC emissions to the control device and maintain control efficiency at or above the demonstrated level or 95 percent, whichever is lower (ii) If the VOC control device is subsequently replaced, the new control device must be at least 95 percent efficient and all VOC emissions must be vented from the total enclosure to the new control device | (a)(2), (b)(5), (c), (d) |
3. If existing coating operation is not in the previous two categories | § 60.712(b)(3) : Recover or destroy at least 93 percent of the VOC applied | (b)(1), (b)(2), (b)(3), (b)(4), (b)(5), (c), (d) |
B. Coating mix preparation equipment alone: | ||
New: | ||
1. With concurrent construction of new VOC control device (other than a condenser) on the coating operation | § 60.712(c) : Install and use covers and vent to a control device that is at least 95 percent efficiente | (b)(6) |
2. Without concurrent construction of new VOC control device on the coating operation or with concurrent construction of a condenser | § 60.712 (d)(1) or (d)(2): Install and use covers and vent to a control device or install and use coverse | (b)(7), (b)(8) |
Modified or reconstructed | § 60.712 (d)(1) or (d)(2): Install and use covers and vent to a control device or install and use coverse | (b)(7), (b)(8) |
C. Both coating operation and coating mix preparation equipment: New and modified or reconstructed | § 60.712(e) : In lieu of standards in § 60.712(a)-(d) , use coatings containing a maximum of 0.20 kg VOC per liter of coating solids | (b)(9) |
a This table is presented for the convenience of the user and is not intended to supercede the language of the regulation. For the details of the requirements, refer to the text of the regulation.
b Refer to part B to determine which subsections of §§ 60.714 , 60.715 , and 60.717 correspond to each compliance provision (§ 60.713 ).
c As per § 60.710(b) , any new coating operation with solvent utilization [LESS THAN]38 m3/yr or any modified or reconstructed coating operation with solvent utilization [LESS THAN]370 m3/yr is exempt from the VOC standards (§ 60.712 ). Such coating operations are subject only to §§ 60.714(a) , 60.717(b) , and 60.717(c) . However, should a coating operation once exceed the applicable annual solvent utilization cutoff, that coating operation shall be subject to the VOC standards (§ 60.712 ) and all other sections of the subpart. Once this has occurred, the coating operation shall remain subject to those requirements regardless of changes in annual solvent utilization.
d As applicable.
e Section 60.716 permits the use of an alternative means of VOC emission limitation that achieves an equivalent or greater VOC emission reduction.
Table 1b-Cross Reference
Compliance provisionsa-§ 60.713 | Test methods-§ 60.715 | Category/equipmentb | Installation of monitoring devices and recordkeeping-§ 60.714 | Reporting and monitoring requirementsc-§ 60.717 |
A. Coating operation alone: | ||||
(b)(1)-When emissions from only the affected coating operation are controlled by a solvent recovery device, perform a liquid-liquid VOC material balance | (a) | (b), (i), (k) | (a), (d)(1), (e), (h), (i) | |
(b)(2)-When emissions from only the affected coating operation are controlled by an incinerator or when a common emission control device (other than a carbon adsorption system with individual exhaust stacks for each adsorber vessel) is used to control emissions from an affected coating operation as well as from other sources of VOC, perform a gaseous emission test | (b)-(g) | General CA CO TI CI PE, TE | (i), (k) (c) (d) (e) (f) (g) | (a), (e), (h), (i) (d)(3), (d)(4) (d)(5) (d)(6) (d)(7) (d)(8) |
(b)(3)-When emissions from both the affected coating operation and from other sources of VOC are controlled by a carbon adsorption system with individual exhaust stacks for each adsorber vessel, perform a gaseous emission test | (b)-(g) | General CA PE, TE | (i), (k) (c) (g) | (a), (e), (h), (i) (d)(3), (d)(4) (d)(8) |
(b)(4)-When emissions from more than one affected coating operation are vented through the same duct to a control device also controlling emissions from nonaffected sources that are vented separately from the affected coating operations, consider the combined affected coating operations as a single emission source and conduct a compliance test described in § 60.713(b)(2) or (3) | (b)-(g) | General CA CO TI CI PE, TE | (i), (k) (c) (d) (e) (f) (g) | (a), (e), (h), (i) (d)(3), (d)(4) (d)(5) (d)(6) (d)(7) (d)(8) |
(b)(5)-Alternative to § 60.713(b)(1)-(4) : Demonstrate that a total enclosure is installed around the coating operation and that all VOC emissions are vented to a control device with the specified efficiency | (b)-(g) | General CA CO TI CI TE | (i), (k) (c) (d) (e) (f) (h) | (a), (e) (h), (i) (d)(3), (d)(4) (d)(5) (d)(6) (d)(7) (d)(8) |
B. Coating mix preparation equipment alone: | ||||
(b)(6)-Demonstrate that covers meeting the requirements of § 60.712(c)(1)-(5) are installed and used properly; procedures detailing the proper use of covers are posted; the mix equipment is vented to a control device; and the control device efficiency is greater than or equal to 95 percent | (b)-(g) | General CA TI CI | (k) (c) (e) (f) | (a), (e), (h), (i) (d)(3), (d)(4) (d)(6) (d)(7) |
(b)(7)-Demonstrate that covers meeting the requirements of § 60.712(c)(1)-(5) are installed and used properly; procedures detailing the proper use of covers are posted; and the mix equipment is vented to a control device. | ||||
(b)(8)-Demonstrate that covers meeting the requirement of § 60.712(c)(1)-(5) are installed and used properly and that procedures detailing the proper use of the covers are posted. | ||||
C. Both coating operation and coating mix preparation equipment: (b)(9)-Determine that weighted average mass of VOC in the coating per volume of coating solids applied for each month | (a) | (i), (j) (k) | (d)(2), (e), (g), (h), (i) |
a Section 60.713(a) specifies the procedures to be used prior to modification/reconstruction to establish the applicability of the VOC standards in § 60.712(b)(1) and (2) for modified/reconstructed coating operations. Section 60.713(a)(1) requires the use of the procedures of § 60.713(b)(1), (2), (3), or (4) to demonstrate prior to modification/reconstruction that 90 percent of the applied VOC is recovered or destroyed. Section 60.713(a)(2) requires the use of procedures of § 60.713(b)(5) to demonstrate prior to modification/reconstruction that the coating operation has a total enclosure vented to a control device that is at least 92 percent efficient. Sections 60.713(c) and (d) do not have corresponding test methods, monitoring, reporting, or recordkeeping requirements.
b TI = thermal incinerator; CI = catalytic incinerator; CA = carbon adsorber; CO = condenser; PE = partial enclosure; TE = total enclosure.
c See § 60.717(f) for additional reporting requirements when coating mix preparation equipment is constructed at a time when no coating operation is being constructed. See § 60.717(g) for addition reporting requirements when coating mix preparation equipment is constructed at the same time as an affected coating operation.
40 C.F.R. §60.711