40 C.F.R. § 60 app Table 1 to Subpart MMMM of Part 60

Current through July 31, 2024
Appendix Table 1 to Subpart MMMM of Part 60 - Model Rule-Increments of Progress and Compliance Schedules for Existing Sewage Sludge Incineration Units

Comply with these increments of progressBy these datesa
Increment 1-Submit final control plan(Dates to be specified in state plan)
Increment 2-Final compliance(Dates to be specified in state plan)b

a Site-specific schedules can be used at the discretion of the state.

b The date can be no later than 3 years after the effective date of state plan approval or March 21, 2016 for SSI units that commenced construction on or before October 14, 2010.

40 C.F.R. 60 app Table 1 to Subpart MMMM of Part 60