Section 60.2190 - What must I submit prior to commencing construction?

You must submit a notification prior to commencing construction that includes the five items listed in paragraphs (a) through (e) of this section:

(a) A statement of intent to construct;
(b) The anticipated date of commencement of construction;
(c) All documentation produced as a result of the siting requirements of § 60.2050 ;
(d) The waste management plan as specified in §§ 60.2055 through 60.2065 ; and
(e) Anticipated date of initial startup.