40 C.F.R. § 51.261

Current through September 30, 2024
Section 51.261 - Final compliance schedules
(a) Unless EPA grants an extension under subpart R, compliance schedules designed to provide for attainment of a primary standard must-
(1) Provide for compliance with the applicable plan requirements as soon as practicable; or
(2) Provide for compliance no later than the date specified for attainment of the primary standard under;
(b) Unless EPA grants an extension under subpart R, compliance schedules designed to provide for attainment of a secondary standard must-
(1) Provide for compliance with the applicable plan requirements in a reasonable time; or
(2) Provide for compliance no later than the date specified for the attainment of the secondary standard under § 51.110(c) .

40 C.F.R. §51.261