38 C.F.R. § 74.11

Current through November 30, 2024
Section 74.11 - How does CVE process applications for VIP Verification Program?
(a) The Director, CVE, is authorized to approve or deny applications for VIP Verification. CVE will receive, review, and examine all VIP Verification applications. Once an applicant registers, CVE will contact the applicant within 30 days to initiate the process. If CVE is unsuccessful in its attempts to contact the applicant, the application will be administratively removed. If CVE is successful in initiating contact with the applicant, CVE will advise the applicant of required documents and the timeline for submission. If the applicant would be unable to provide conforming documentation, the applicant will be given the option to withdraw its application. CVE will process an application for VIP Verification status within 90 application days, when practicable, of receipt of a registration. Incomplete application packages will not be processed.
(b) CVE, in its sole discretion, may request clarification of information relating to eligibility at any time in the eligibility determination process. CVE will take into account any clarifications made by an applicant in response to a request for such by CVE.
(c) CVE, in its sole discretion, may request additional documentation at any time in the eligibility determination process. Failure to adequately respond to the documentation request shall constitute grounds for a denial or administrative removal.
(d) An applicant's eligibility will be based on the totality of circumstances existing on the date of application, except where clarification is made pursuant to paragraph (b) of this section, additional documentation is submitted pursuant to paragraph (c) of this section, as provided in paragraph (e) of this section or in the case of amended documentation submitted pursuant to § 74.13(a) . The applicant bears the burden to establish its status as a VOSB.
(e) Changed circumstances for an applicant occurring subsequent to its application and which affect eligibility will be considered and may constitute grounds for denial of the application. The applicant must inform CVE of any changed circumstances that could affect its eligibility for the program (i.e., ownership or control changes) during its application review.
(1)Bankruptcy. Bankruptcy is a change in circumstance requiring additional protection for the agency. Should a VOSB enter into bankruptcy the participant must:
(i) Inform CVE of the filing event within 30 days;
(ii) Specify to CVE whether the concern has filed Chapter 7, 11, or 13 under U.S. Bankruptcy code; and
(iii) Any participant that is performing contracts must assure performance to the contracting officer(s) prior to any reorganization or change if necessary including such contracts in the debtor's estate and reorganization plan in the bankruptcy.
(2) [Reserved]
(f) The decision of the Director, CVE, to approve or deny an application will be in writing. A decision to deny verification status will state the specific reasons for denial and will inform the applicant of any appeal rights.
(g) If the Director, CVE, approves the application, the date of the approval letter is the date of participant verification for purposes of determining the participant's verification eligibility term.
(h) The decision may be sent by mail, commercial carrier, facsimile transmission, or other electronic means. It is the responsibility of the applicant to ensure all contact information is current in the applicant's profile.

38 C.F.R. §74.11

83 FR 48230 , Sept. 24, 2018
83 FR 48230 , 10/1/2018

The Office of Management and Budget has approved the information collection requirements in this section under control number 2900-0675