33 C.F.R. § 155.1135

Current through May 31, 2024
Section 155.1135 - Response plan development and evaluation criteria

For tankers subject to this subpart, the following response times must be used in determining the on-scene arrival time in Prince William Sound, for the response resources required by § 155.1050 :

Tier 1Tier 2Tier 3
Prince William Sound12 hrs24 hrs36 hrs

33 C.F.R. §155.1135