Section 154.2200 - Applicable transfer facility design and installation requirements

A tank barge cleaning facility's (TBCF's) vapor control system (VCS) must meet the following design and installation requirements of this subpart for a transfer facility's VCS:

(a)33 CFR 154.2100(b), (c), (f), (g), (i), (j), and (k) : general design and installation requirements;
(b)33 CFR 154.2102 : facility requirements for vessel liquid overfill protection, if a TBCF receives vapor from a tank barge that is required by 46 CFR 39.6001(f)(3) to be equipped with a liquid overfill protection arrangement and meet 46 CFR 39.2009 ;
(c)33 CFR 154.2106 : detonation arrester installation;
(d)33 CFR 154.2107 : inerting, enriching, and diluting systems;
(e)33 CFR 154.2108 : vapor-moving devices;
(f)33 CFR 154.2109 : vapor recovery and vapor destruction units;
(g)33 CFR 154.2111 : VCS connected to a facility's main VCS;
(h)33 CFR 154.2112 : special requirements for vapors with the potential to polymerize or freeze; and
(i)33 CFR 154.2113 : special requirements for alkylene oxides.