Section 585.651 - [Effective until 7/15/2024] When may I construct complex or significant OCS facilities on my limited lease or any facilities on my project easement proposed under my GAP?

If you are applying for a project easement, or installing a facility or a combination of facilities on your limited lease deemed by BOEM to be complex or significant, as provided in § 585.648(a)(1) , you also must comply with the requirements of 30 CFR part 285 , subpart G, and submit your safety management system description required by 30 CFR 285.810 before construction may begin.

30 C.F.R. §585.651

88 FR 6430, 1/31/2023