30 C.F.R. § 585.316

Current through May 31, 2024
Section 585.316 - [Effective 7/15/2024] What payments are required for ROW grants or RUE grants?

Before we issue the ROW grant or RUE grant, you must pay:

(a) Any balance on accepted high bids to Office of Natural Resources Revenue (ONRR), as provided in the sale notice.
(b) An annual rent for the first year of the grant, as specified in § 585.508 .

30 C.F.R. §585.316

89 FR 42735, 7/15/2024