Section 285.905 - When must I submit my decommissioning application?You must submit your decommissioning application upon the earliest of the following dates:
(a) Two (2) years before the expiration of your lease.(b) Ninety (90) days after completion of your commercial activities on a commercial lease.(c) Ninety (90) days after completion of your approved activities under a limited lease on a ROW grant or RUE grant.(d) Ninety (90) days after cancellation, relinquishment, or other termination of your lease or grant.(e) Ninety (90) calendar days after BSEE determines a facility is no longer useful for operations. 88 FR 6413 , 1/31/2023; 89 FR 42721 , 7/15/2024