30 C.F.R. § 285.614

Current through November 30, 2024
Section 285.614 - When may I begin conducting activities under my approved SAP?
(a) You may begin conducting the activities approved in your SAP following BOEM approval of your SAP.
(b) If you are installing a facility or a combination of facilities deemed by BOEM to be complex or significant, as provided in 30 CFR 585.613(a)(1) , you must comply with the requirements of subpart G of this part and submit the Safety Management System (SMS) description required by § 285.810 before construction may begin.

30 C.F.R. §285.614

88 FR 6413 , 1/31/2023; 89 FR 42715 , 7/15/2024